Evander Gold Mine Site Visit and ETRP update 12 February 2015
Shareholders are advised that Pan African will host a site visit to Evander Gold Mines today, where visitors will have the opportunity to go on an underground tour of the operations at No 8 shaft and a surface tour of the “Evander Tailings Retreatment Plant” (ETRP). An overview of the mine and the ETRP will be presented after the surface tour. No material new information will be given during the site visit. A copy of the presentation is now available.
Pan African is also proud to announce that the first gold at the ETRP was produced in January 2015 after the commencement of re-treating slimes from the Kinross tailings dam. The ETRP is expected to reach a steady state of production of between 180,000 to 200,000 tonnes per month by June 2015.
To view the presentation click here.