Pan African is a mining company with operations solely in Africa.

Mining Operations

 
   

Country

Name

%
Stake

Production
Ounces

EBITDA
(30 June 2009)
Unaudited

Total
Resource

   

South Africa

Barberton Mines (Pty) Ltd

Three operational gold
mines: Fairview, Sheba
and New Consort

100

~100,000 oz per annum

£17.8 million

2,014,000 oz

 
 
   

Overview
Vision & Strategy
Company Structure
Board of Directors
Management
Black Economic Empowerment

 

       

 

     

Phoenix Platinum Project (South Africa) - Milestones Achieved

 

 

     

 

 

 

         

Key Events

Achievement

Completion Date

Comments

 

 

         

CTRP site negotiation

Concluded agreement
with International
Ferro Metals SA (Pty)
Ltd (‘IFM’)

5 November 2010

Total consideration of ZAR80 million (£7.2 million) payable in tranches as follows:

payment of ZAR25 million (£2.24 million) paid on signature

ZAR25 million (£2.24 million) on commencement of bulk earthworks

ZAR500,00 (£0.05 million) to purchase the site property, payable on transfer

ZAR29.5 million (£2.64 million) on commissioning of CTRP

 

 

         

Project
review

Independent overall
review by Venmyn
Rand (Pty) Ltd

1 August
2010

Review concluded that there were no fatal flaws in the information reviewed

 

 

         

 

Detail engineering
design

July
2010

Design review completed by external experts led to minor design changes

 

 

         

Final capital expenditure

Capital estimate

August
2010

Estimated ZAR104 million

 

 

         

 

Concluded capital construction and
execution agreement

18 November 2010

Lump sum turnkey contract concluded with Matomo Projects (Pty) Ltd

 

 

         

Commenced construction

Site establishment

18 November 2010

Procurement and long lead item phase commenced

 

 

     

 

 

 

     

Phoenix Platinum Project (South Africa) - Milestones Planned

 

 

     

 

 

 

         

Key Events

Objective

Estimated Completion Date

 

 

         

Procurement

Conclude procurement of long lead items (feed
thickener, ultra fine grind mill and flotation cells)

Complete

 

 

         

Detail design

Finalise construction drawings and diagrams on
receipt of vendor drawings

Complete

 

 

         

Commence
CTRP construction

Bulk earthworks on site and civil engineering

Commence mechanical construction and erection

Mid-March 2011

Mid-May 2011

 

 

         

Commissioning

Complete construcition and start cold commissioning

October 2011

 

 

         

Full production

Achieve planned production rate

Q1 2012

 

 

       

 

     

Manica Gold Project (Mozambique) - Project Schedule

 

 

     

 

 

 

         

Key Events

Completion Date

Progress

 

 

         

Metallurgical test work

October 2010

 

 

         

Mine design

November 2010

 

 

         

Plant design

November 2010

 

 

         

Engineering design

November 2010

 

 

         

Completion of pre-feasibility - open pit

December 2010

 

 

         

Environmental impact assessment

June 2011

 

 

     

 

 

UK (AIM): PAF | SA (JSE): PAN

Tel: + 27 11 243 2900 | Fax: + 27 11 880 1240 | Copyright © Pan African Resources PLC 2012 | Disclaimer | Terms of use | Privacy Policy
webmaster@panafricanresources.com